General turnaround 2013 FCC and auxiliaries plants – Priolo Gargallo Refinery

Customer: Isab S.r.l.

Site: Priolo Gargallo (SR)

Period: from March 15th, 2013 to April 04rd, 2013

154.000

MANHOURS/TURNAROUND

605

PEAK TURNAROUND (PEOPLE)

93.000

MANHOURS/SLOWDOWN

550

PEAK SLOWDOWN (PEOPLE)

The scope of work included the following activities:

“Catalytic Area”:

– Supply and replacement of Co-Boiler pressure components

– Prefabrication and assembling of CO-Boiler piping and structures modification

– Ri-generator, stand pipe and internal cyclone maintenance activities

– Reactors and internal cyclones maintenance activities

– Column C201 internal parts maintenance and replacement

– Heat exchangers and vessels maintenance

– Insulation activities

– Scaffolding, assistance and auxiliaries works

– Upholsteries, refractories and anti-abrasive refurbishment

– Piping and equipment sandblasting and painting

– Equipment internal cleaning and catalyzer removal

– Electro-instrumental activities

– Non-destructive testing

– CO-Boiler commissioning

– Repair service and CO-Boiler requalification according to Pressure Equipment Directive

 

“Distillation Area”:

– Accumulators, heat-exchangers and air fins maintenance and piping replacement (n. 94)

– Columns maintenance (n. 11)

– Piping replacement, dismantling, prefabrication and assembling

– Piping and structures new investments

– Pressure Equipment Directive and D.M. 329  implementation

– Insulation activities

– Scaffolding, assistance and auxiliaries works

– Non-destructive testing

– Pre-commissioning activities