| Start |
End |
Project Description |
Client |
Site |
| 2008 |
2011 |
New Vacuum Plant |
ENI |
Sannazzaro de' Burgondi (PV) |
| 2008 |
2009 |
Turn-key supply of biomass plant for power generation (6 MWe) |
Fusine Energia |
Fusine |
| 2007 |
2008 |
Turn-key supply of a 120 Mw thermal plant for the district heating network in Mantova |
Enipower |
Mantova |
| 2007 |
2008 |
Turn-key supply of a 12 MWt biomass power plant for district heating network |
T.C.V.V.V. |
Santa Caterina (SO) |
| 2004 |
2008 |
Turn-key supply of technological plants for the new hospital in Albenga |
ASL II Savona |
Albenga (SV) |
| 2004 |
2006 |
Turn-key supply of a 255 Mw thermal plant as an integration and reserve to the district heating network of Turin |
AEM Torino |
Turin |
| 2003 |
2004 |
Turn-key supply of various refinery plants |
ExxonMobil |
Augusta (SR) |
| 2003 |
2003 |
Engineering of BOP to HRGT at Sermide plant |
Enelpower |
Sermide (MN) |
| 2003 |
2003 |
Various plant modifications |
ENI |
Porto Torres (SS) |
| 2003 |
2003 |
Various plant modifications |
ENI |
Rho (MI) |
| 2003 |
2003 |
Various plant modifications |
ENI |
Ortona (CH) |
| 2003 |
2003 |
Various modifications and interventions also on oil pipeline |
Petrolig |
Vado Ligure (SV) |
| 2002 |
2005 |
Turn-key supply of ventilation and air-conditioning plants for points 1 and 5 of experimental area |
CERN |
Ginevra (CH) |
| 2002 |
2003 |
Turn-key supply of technologic plants (cooling system to -48°C, storage and loading) of M/S Marola |
Fincantieri |
Ancona |
| 2002 |
2003 |
Design, engineering and assistance with the construction of new plant for the production of sodium percarbonate |
MedAvox |
Bussi (PE) |
| 2002 |
2002 |
Various plant modifications |
ENI |
Calenzano (FI) |
| 2002 |
2002 |
Various plant modifications |
ENI |
Stagno (LI) |
| 2002 |
2002 |
Various plant modifications, adaptation of loading bays to regulations. |
ENI |
Rho (MI) |
| 2002 |
2002 |
Various plant modifications |
ENI |
Porto Torres (SS) |
| 2002 |
2002 |
Modifications on VRU plant |
ENI |
Ponte Galeria (Roma) |
| 2002 |
2002 |
Modifications on various plants, modifications on VRU plant |
ENI |
Ortona (CH) |
| 2002 |
2002 |
Various plant modifications |
ENI |
Fiorenzuola (PC) |
| 2002 |
2002 |
Various plant modifications, various interventions on oil pipelines |
ENI |
Arcola (SP) |
| 2002 |
2002 |
Project for zinc expansion |
Infineum |
Vado Ligure (SV) |
| 2002 |
2002 |
M.A. Recovery System |
Infineum |
Vado Ligure (SV) |
| 2002 |
2002 |
Modifications on various plants, modifications on VRU plant |
Petrolig |
Calata Canzio (GE) |
| 2002 |
2002 |
Various plant modifications, various interventions on oil pipelines |
Petrolig |
Vado Ligure (SV) |
| 2002 |
2002 |
Various plant modifications |
Petroven |
Venezia |
| 2001 |
2007 |
Engineering services |
Infineum |
Vado Ligure (SV) |
| 2001 |
2002 |
Turn-key supply of GPL deposit area and production site redesign |
AgipGas |
Ravenna |
| 2001 |
2002 |
Turn-key supply of ventilation and air-conditioning plants - for the new optical fiber production plant |
Pirelli |
Battipaglia (NA) |
| 2001 |
2001 |
Feasibility study for Cremona deposit |
ENI |
Cremona |
| 2001 |
2001 |
Various plant modifications, adaptation of loading bays to regulations. |
ENI |
Rho (MI) |
| 2001 |
2001 |
Various plant modifications, adaptation of loading bays to regulations, modification on VRU plant |
ENI |
Porto Torres (SS) |
| 2001 |
2001 |
Safety interventions |
ENI |
Pomezia (LT) |
| 2001 |
2001 |
Various plant modifications, various interventions on oil pipelines |
ENI |
Napoli |
| 2001 |
2001 |
Various plant modifications |
ENI |
Genova |
| 2001 |
2001 |
Various plant modifications, adaptation of loading bays to regulations, modification on VRU plant |
ENI |
Fiorenzuola (PC) |
| 2001 |
2001 |
Various plant modifications |
ENI |
Calenzano (FI) |
| 2001 |
2001 |
Various plant modifications |
ENI |
Arcola (SP) |
| 2001 |
2001 |
Thermal dispersant project |
Infineum |
Vado Ligure (SV) |
| 2001 |
2001 |
Various plant modifications |
Petrolig |
Vado Ligure (SV) |
| 2001 |
2001 |
Various plant modifications |
Petrolig |
Calata Canzio (GE) |
| 2001 |
2001 |
Various plant modifications |
Petroven |
Venezia |
| 2001 |
2001 |
Turn-key supply of organic cycles plant for the production of electric energy (1,1 MWe) |
T.C.V.V.V. |
Tirano (SO) |
| 2000 |
2008 |
Engineering services |
ExxonMobil |
Trecate (NO) |
| 2000 |
2001 |
Revamping of bitumen plant |
Esso Italiana |
Trecate (NO) |
| 2000 |
2001 |
Turn-key supply of plant for distribution, storage, load and unload of solvents |
ExxonMobil |
Trecate (NO) |
| 2000 |
2001 |
Turn-key supply of new automatic batch blending unit for lubricating oils |
Infineum |
Vado Ligure (SV) |
| 2000 |
2000 |
Various projects |
Aventis Bulk |
Garessio (CN) |
| 2000 |
2000 |
Various plant modifications, adaptation of loading bays to regulations, modification on VRU plant |
ENI |
Rho (MI) |
| 2000 |
2000 |
Various plant modifications |
ENI |
Calata Canzio (GE) |
| 2000 |
2000 |
Various plant modifications |
ENI |
Genova |
| 2000 |
2000 |
Various plant modifications, adaptation of loading bays to regulations, modification on VRU plant |
ENI |
Venezia |
| 2000 |
2000 |
Various plant modifications |
ENI |
Vado Ligure (SV) |
| 2000 |
2000 |
Adaptation of loading bays to regulations. |
ENI |
Gela (SR) |
| 2000 |
2000 |
Various plant modifications |
ENI |
Fiorenzuola (PC) |
| 2000 |
2000 |
Various plant modifications |
ENI |
Sannazzaro de' Burgondi (PV) |
| 2000 |
2000 |
Various plant modifications |
ENI |
Calenzano (FI) |
| 2000 |
2000 |
Various plant modifications, adaptation of loading bays to regulations, modification on VRU plant |
Petrolig |
Venezia |
| 2000 |
2000 |
Various plant modifications, adaptation of loading bays to regulations, modification on VRU plant |
Petrolig |
Vado Ligure (SV) |
| 1999 |
2001 |
Various plant revamping |
Agippetroli |
Rho (MI), Ravenna Fiorenzuola (PC) |
| 1999 |
2001 |
Turn-key supply of 12 MWt biomass power plant for district heating network |
T.C.V.V.V. |
Tirano (SO) |
| 1999 |
2001 |
Turn-key supply of 12 MWt biomass power plant for district heating network |
T.C.V.V.V. |
Sondalo (SO) |
| 1999 |
1999 |
Plant P2S5 |
Agippetroli |
Robassomero (TO) |
| 1999 |
1999 |
Various plant modifications |
ENI |
Vado Ligure (SV) |
| 1999 |
1999 |
Various plant modifications |
ENI |
Venezia |
| 1999 |
1999 |
Various plant modifications |
ENI |
Rho (MI) |
| 1999 |
1999 |
Various plant modifications |
ENI |
Ravenna |
| 1999 |
1999 |
Various plant modifications |
ENI |
Portogruaro (VE) |
| 1999 |
1999 |
Various plant modifications |
ENI |
Sannazzaro de' Burgondi (PV) |
| 1999 |
1999 |
Various plant modifications |
ENI |
Genova |
| 1999 |
1999 |
Various plant modifications |
ENI |
Calenzano (FI) |
| 1999 |
1999 |
Modifications on VRU plant |
Petroven |
Venezia |
| 1998 |
1999 |
Turn-key supply of plant for the production of emulsion for audiovisual supports |
3M Italia |
Caserta |
| 1997 |
1997 |
Reception DPV/ESAR |
Agippetroli |
Sannazzaro de' Burgondi (PV) |
| 1997 |
1997 |
Water barriers alkylation plant |
Agippetroli |
Sannazzaro de' Burgondi (PV) |
| 1997 |
1997 |
Employment of concentrated sulphonic acid |
Agippetroli |
Robassomero (TO) |
| 1997 |
1997 |
Blending Plant |
Agippetroli |
Robassomero (TO) |
| 1996 |
1997 |
Engineering and assistance for the construction of technological and process plant for Mojokerto and Perawang papermills |
Beloit Italia |
Perawang and Mojokerto (Indonesia) |
| 1996 |
1997 |
On site & Off site Genesis Project |
Foster Wheeler |
Vado Ligure (SV) |
| 1996 |
1996 |
Capacity expansion of OCPVI plant |
Agippetroli |
Robassomero (TO) |
| 1996 |
1996 |
Various projects |
Gruppo Lepetit |
Garessio (CN) |
| 1996 |
1996 |
Revamping of exhaust water plant |
SISAS |
Limito (MI) |
| 1995 |
1997 |
Turn-key supply of wool cleaning plant (solvent based) and connected plant for wool carding and combing |
Wooltech Europe |
Trieste |
| 1995 |
1995 |
Blending automatic batch plant |
Exxon Chemical Mediterranea |
Vado Ligure (SV) |
| 1994 |
2005 |
Various projects |
Solvay Solexis |
Spinetta Marengo (AL) |
| 1994 |
1995 |
Engineering of combined cycles BOP in the FIAT Auto premises in Termoli, Melfi, Rivalta Torinese and Sulmona. |
Fiat Avio |
Various |
| 1994 |
1995 |
Reconstruction of Scrivia riverside |
Iplom |
Busalla (GE) |
| 1993 |
1995 |
Blending plant for lubricating oil |
Cellier |
Taiz - Yemen |
| 1992 |
1993 |
Turn-key supply of the expansion to 30.000 t/year of production plant for sulphonated calcium and adjustmend to plant utilities |
AgipPetroli |
Robassomero (TO) |
| 1991 |
1992 |
Engineering of combined cycle BOP at the premise in Bussi |
Edison |
Bussi (PE) |
| 1989 |
1989 |
Plant for production of additive benzine |
Exxon Chemical Mediterranea |
Vado Ligure (SV) |
| 1988 |
2000 |
Various projects |
Exxon Chemical Mediterranea |
Vado Ligure (SV) |